Kapeeka ss

11:44 Aug 1 2014 Kapeeka, Nakaseke

Description
Scope: 8 classrooms, and 3 no. 5-stance lined VIP latrine blocks.

Contract signed: N/A. Site handed over: N/A. Works commenced: N/A. Original completion date: N/A. Revised completion date: 31-Dec-2012.

Contract sum: UGX 262,032,810. Amount released to school: UGX 262,032,810 (UGX 131,016,405 on 25-Apr-2012 and UGX 131,016,405 on 12-Mar-2013). Amount accounted for: UGX 246,032,810 (94%). Outstanding advance: UGX 16,000,000 (06%).

Physical progress: 100%. Furniture supplied.

10,000 litre rain water tank installed by CRESTANKS.

Follow up actions:

(i) School to submit final accountability to the Ministry.

(ii) Ministry to issue final certificate to the school.
Additional Data
Phase: II
Contractor: KSD Builders, Constructors and Estate Developers Ltd
Works Compliant with Specifications: Yes
Project Status: complete
School Completed (with Furnishing)?: Yes
Exp. Date of Completion: Oct 27 2014

Credibility: UP DOWN 0
Leave a Comment
Name:
Email:
Comments:
Security Code:
Captcha

Additional Reports

Kijaguzo ss

12:53 Aug 01, 2014

Semuto, Nakaseke, 6.41 Kms

BANANYWA ST. MATHIAS PRIMARY SCHOOL

16:23 Aug 31, 2016

Namayumba, Wakiso, 10.53 Kms

Semu Muwanguzi

14:58 Oct 08, 2014

Kikyusa, Luweero, 10.69 Kms

Kiwoko ss

12:45 Jul 16, 2014

Kikamulo, Nakaseke, 14.38 Kms

Kiwoko SS

12:50 Sep 27, 2013

Kikamulo, Nakaseke, 14.4 Kms