St. Mugaga SS

15:50 Aug 25 2014 Kiganda, Mubende

Description
Scope: 8 classrooms, 1 laboratory, 1 Administration block, and 3 no. 5-stance lined VIP latrine blocks.

Contract signed: N/A. Site handed over: N/A. Works commenced: 29-Mar-2012. Original completion date: 05-Jul-2012. Revised completion date: 31-Dec-2012.

Contract sum: UGX 480,562,000. Amount released to school: UGX 480,562,000 (1st 50% on 06-Aug-2012 and 2nd 50% on 06-Jun-2013). Amount accounted for: UGX 480,511,526 (99.9%). Outstanding advance: UGX 50,474 (0.1%).

Physical progress: 100%.

10,000 litre rain water tank installed by CRESTANKS.

Follow up actions:

(i) School to budget for operation and maintenance of facilities.
Additional Data
Phase: II
Contractor: Kiyinda Carpentry Workshop and Contractors
Works Compliant with Specifications: Yes
Project Status: complete
School Completed (with Furnishing)?: Yes
Exp. Date of Completion: Jan 01 1970

Credibility: UP DOWN 0
Leave a Comment
Name:
Email:
Comments:
Security Code:
Captcha

Additional Reports

Mubende Light SS

16:30 Aug 25, 2014

Mubende Town Council, Mubende, 2.04 Kms

butoloogo seed ss

08:00 Aug 25, 2014

Butologo, Mubende, 2.16 Kms

BUBAMBA PRIMARY SCHOOL

16:54 Sep 29, 2015

Nyamarwa, Kibaale, 17.79 Kms

Kamusenene Primary School

11:35 Sep 01, 2016

Kitumbi, Mubende, 26.87 Kms

St. Michael Primary School Kamusenene

12:26 Sep 01, 2016

Kitumbi, Mubende, 27.69 Kms