Verified

St. Mark SS Kammengo

08:29 Sep 9 2014 Kammengo, Mpigi

Description
Scope: 6 classrooms, 1 administration block, 1 library, and 2 no. 5-stance lined VIP latrine blocks.

Contract signed: 4-Jul-2012. Site handed over: xx. Works commenced: 11-Jul-2012. Original completion date: 16-Aug-2013. Revised completion date: xx.

Contract sum: UGX 1,059,202,100. Amount released to school: UGX 1,059,202,100 (1st 50% on08-Aug-2012 and 2nd 50% on 18-Jun-2013). Amount accounted for: UGX 964,783,875 (91%). Outstanding advance: UGX 94,418,225 (9%).

Physical progress: 100%.

10,000 litre rain water tank installed by CRESTANKS.

UMEME power connected.

Follow up actions:

(i) completed, furniture supplied partially for classrooms and library, office furniture not yet delivered, in detects liability period, poor quality furniture, finishes on buildings not satisfactory.

(ii) Contractor to correct identified defects.
Additional Data
Phase: I
Contractor: Build Base Contractors Ltd
Works Compliant with Specifications: Yes
Project Status: complete
School Completed (with Furnishing)?: Yes
Exp. Date of Completion: Aug 09 2014

Credibility: UP DOWN 0
Comments
Sukhie Brar (Jun 24 2015)
Looks very nice!
Comment Rating: UP DOWN
0
Leave a Comment
Name:
Email:
Comments:
Security Code:
Captcha

Additional Reports

ST. MARIA MULUMBA PRIMARY SCHOOL

17:46 Sep 01, 2016

Malangala, Mityana, 12.51 Kms

Entebbe Comprehensive SS

14:19 Dec 02, 2014

Division B Entebbe, Wakiso, 16.42 Kms

Entebbe Comprehensive SS

11:35 Jun 06, 2014

Division B, Entebbe Municipality, 16.43 Kms

NANKONGE PRIMARY SCHOOL

12:42 Aug 31, 2016

Ssisa, Wakiso, 17.13 Kms

Airforce SS

16:50 Jun 04, 2014

Division A, Entebbe Municipality, 17.97 Kms