Adilang SS

14:28 Sep 2 2014 Adilang, Agago

Description
Scope: 4 classrooms, 1 laboratory, and 2 no. 5-stance lined VIP latrine blocks.

Contract signed: 01-Dec-2011. Site handed over: 27-Mar-2012. Works commenced: 03-Apr-2012. Original completion date: 29-Aug-2012. Revised completion date: 29-Dec-2012 .

Contract sum: UGX 320,243,900. Amount released to school: UGX 320,243,900 (1st 50% on 22-Jun-2012 and 2nd 50% on 11-Mar-2013). Amount accounted for: UGX 131,176,446 (41%). Outstanding advance: UGX 189,067,454 (59%).

Physical progress: 100%.

completed with furniture,in detects liability period, 2 rain water tanks installed, solar power installed by ERT,UMEME connected.

Follow up actions:

(i) Head teacher to submit final accountability.
Additional Data
Phase: II
Contractor: Tem Gumi Co. Ltd
Works Compliant with Specifications: Yes
Project Status: complete
School Completed (with Furnishing)?: Yes
Exp. Date of Completion: Aug 02 2014

Credibility: UP DOWN 0
Leave a Comment
Name:
Email:
Comments:
Security Code:
Captcha

Additional Reports

Adilang SS

14:20 Feb 18, 2015

Adilang, Agago, 0.01 Kms

Adilang SS

13:17 Sep 21, 2013

Pader town, 0.18 Kms

Patongo SS

13:16 Sep 21, 2013

Pader town, 11.89 Kms

Abim Secondary School

12:18 Sep 12, 2013

Abim Town Council, 12.79 Kms

Lotuke Seed SS

12:07 Sep 02, 2014

Lotukei, Abim, 16.44 Kms