Verified

Lukome SS

11:13 Jun 27 2014 Bungatira, Gulu

Description
Scope: 4 classrooms, 1 laboratory, and 2 no. 5-stance lined VIP latrine blocks.

Contract signed: 11-Jan-2012. Site handed over: 11-Sep-2012. Works commenced: 11-Sep-2012. Original completion date: 23-Feb-2013. Revised completion date 1: 14-Jun-2013. Revised completion date 2: 21-Jan-2014.

Contract sum: UGX 312,655,300. Amount released to school: UGX 312,655,300 (1st 50% on 26-Nov-2012 and 2nd 50% on03-Oct-2013). Amount accounted for: UGX 188,552,520 (60%). Outstanding advance: UGX 124,102,780 (40%).

Total expenditure UGX 243,109,260. Expected balance UGX 69,545,680.

UMEME power extended but not yet connected. Water supply by borehole. Solar power installed by ERT project.

Contractor submitted payment claim on 17-Feb-2014 but not yet certified.

Physical progress: 100%.

10,000 litre Rain water tank installed by CRESTANKS.

Follow up actions:

(i) School to submit accountability for additional expenditure.

(ii) Ministry to issue certificate for works executed to date.
Additional Data
Phase: II
Contractor: Watwero Enterprises Ltd
Works Compliant with Specifications: Yes
Project Status: complete
School Completed (with Furnishing)?: Yes
Exp. Date of Completion: Jul 01 2014

Credibility: UP DOWN 0
Leave a Comment
Name:
Email:
Comments:
Security Code:
Captcha

Additional Reports

Gulu SS

09:46 Jun 27, 2014

Bar Dege Division, Gulu Municipality, Gulu, 8.5 Kms

Awach SS

12:56 Jun 27, 2014

Awach, Gulu, 8.58 Kms

Koro SS

14:58 Jun 26, 2014

Koro, Gulu, 12.85 Kms

Opit SS

16:24 Jun 26, 2014

Lakwana, Gulu, 23.36 Kms