Opit SS

16:24 Jun 26 2014 Lakwana, Gulu

Description
Scope: 10 classrooms, 1 laboratory, 1 Admin block and 2 no. 5-stance lined VIP latrine blocks.

Contract signed:05-Nov-2012. Site handed over: 19-Dec-2012. Works commenced:19-Dec-2012. Original completion date: 17-Jun-2013. Revised completion date: 24-Oct-2013 .

Contract sum: UGX 627,159,572. Amount released to school: UGX 313,579,786 (1st 50% on 21-Dec-2012). Amount accounted for: UGX 213,653,406 (68%). Outstanding advance: UGX 99,926,380 (32%).

Performance security issued by EXCEL INSURANCE COMPANY LIMITED on 27-Sep-2013 expires on 27-Nov-2014.

Physical progress: 50%. slow progress.

Rain water tank not yet delivered. Furniture sample not yet delivered.

Follow up actions:

(i) Ministry to release second tranche to school.

(ii) Contractor to correct identified defects in the science laboratory.

(ii) Contractor to deploy heavily for timely completion of works.

(iv) M/S CRESTANKS to deliver and install rain water tank on any suitable existing building at the school.
Additional Data
Phase: II
Contractor: Charbod (U) Ltd
Works Compliant with Specifications: No
Project Status: in-progress
Resources on Site: Material
Performance of Contractor: Lagging
School Completed (with Furnishing)?: No
Exp. Date of Completion: Aug 31 2014

Credibility: UP DOWN 1
Leave a Comment
Name:
Email:
Comments:
Security Code:
Captcha

Additional Reports

St. Thomas Moore Secondary School Minakulu

11:16 Mar 11, 2015

Bobi, Gulu, 10.85 Kms

Koro SS

14:58 Jun 26, 2014

Koro, Gulu, 10.92 Kms

Iceme Girls SS

13:10 Jun 26, 2014

Iceme, Oyam, 12.93 Kms

Gulu SS

09:46 Jun 27, 2014

Bar Dege Division, Gulu Municipality, Gulu, 16.37 Kms