Scope: 4 classrooms, 1 laboratory, and 2 no. 5-stance lined VIP latrine blocks.

Contract signed: 30-Dec-2011 . Site handed over: 30-Dec-2011 . Works commenced:01-Jun-2012. Original completion date: 07-Jul-2012. Revised completion date 1: 31/8/2011. Revised completion date 2: 30/11/2012.

Contract sum: UGX 308,511,900. Amount released to school: UGX 308,511,900 (1st 50% on 28-Feb-2012 and 2nd 50% on 22-Jun-2012). Amount accounted for: UGX 248,278,304 (80%). School returned project balance of UGX 60,233,596 on 13-Jun 2014.

Physical progress: 80%. Contract terminated on 22-Oct-2013. Pending works include mechanical installations in the science laboratory and general supply of furniture.

Solar power installed by ERT project. Water supply by borehole.

Follow up actions:

(i) Ministry to budget and secure replacement contractor under centralised procurement for completion of pending works.
Additional Data
Phase: II
Contractor: Opit & Sons Millers Limited
Works Compliant with Specifications: Yes
Project Status: stalled
School Completed (with Furnishing)?: No
Exp. Date of Completion: Mar 31 2015

Credibility: UP DOWN 0
Leave a Comment
Name:
Email:
Comments:
Security Code:
Captcha

Additional Reports

Gulu SS

09:46 Jun 27, 2014

Bar Dege Division, Gulu Municipality, Gulu, 5.48 Kms

Opit SS

16:24 Jun 26, 2014

Lakwana, Gulu, 10.92 Kms

Lukome SS

11:13 Jun 27, 2014

Bungatira, Gulu, 12.85 Kms

St. Thomas Moore Secondary School Minakulu

11:16 Mar 11, 2015

Bobi, Gulu, 15.84 Kms