KITOORO PRIMARY SCHOOL

13:22 Aug 3 2016 Nyamarebe, Ibanda

Description
Field appraisal site visit (FASV) conducted in September 2015.

Enrolment (at the time of FASV) 227 pupils (126 girls & 101 boys)

5 Acres are available for GPE project construction activities. Letter from foundation body – Church of Uganda (Bihanga Parish) available.

Challenges encountered/issues arising:

- Block 1 is earmarked for demolition.
- Gentle slope: 1 in 20
- Normal soils

Recommendations:

The school should benefit from GPE project facilities.


Follow up stakeholders consultations undertaken at the school on 3rd August 2016.
Additional Data
Project Status: Not Started
Functionality of SMC: Active
Equipment on Site: None
Workers on Site: None
Contractors Name: not yet appointed
Contract Sum: na
Certified Payment: na
Exp. Date - Performance Security: Jul 03 2016

Credibility: UP DOWN 0
Leave a Comment
Name:
Email:
Comments:
Security Code:
Captcha

Additional Reports

KATENGYETO PRIMARY SCHOOL

14:27 Aug 03, 2016

Ishongororo, Ibanda, 1.48 Kms

KEMIHOKO PRIMARY SCHOOL

17:03 Aug 02, 2016

Ishongororo Town Council, Ibanda, 2.91 Kms

ISHONGORORO PRIMARY SCHOOL

18:50 Aug 02, 2016

Ishongororo Town Council, Ibanda, 4.04 Kms

KYEIBUMBA PRIMARY SCHOOL

17:57 Aug 02, 2016

Nyamarebe, Ibanda, 5.86 Kms

Bigyera SS

17:12 May 28, 2014

Bisheshe, Ibanda, 8.58 Kms