Field appraisal site visit (FASV) conducted in September 2015.

Enrollment (at the time of FASV) 370 pupils (178 girls & 192 boys)

About 5 Acres have been set aside for GPE project construction activities. Letter from foundation body – Catholic Church available.

Challenges encountered/issues arising:

- Sloppy ground: 1 in 15
- Normal soils
- Uprooting trees to create access to site around 15 nos mature cypress
- No staff accommodation.

Recommendation:

The school qualifies for GPE project facilities.

Follow up stakeholders consultations undertaken at the school on 2nd August 2016.
Additional Data
Project Status: Not Started
Functionality of SMC: Active
Equipment on Site: None
Workers on Site: None
Contractors Name: not yet appointed
Contract Sum: na
Certified Payment: na
Exp. Date - Performance Security: Jul 02 2016

Credibility: UP DOWN 0
Leave a Comment
Name:
Email:
Comments:
Security Code:
Captcha

Additional Reports

burambagira ss

16:50 Aug 18, 2014

Ngamba, Bundibugyo, 3.93 Kms

Nyabuhikye ss

16:55 Aug 18, 2014

Nyabuhikye, Ibanda, 4.06 Kms

Mwamba SS

10:09 May 28, 2014

Rukiri, Ibanda, 4.13 Kms

Nyabuhikye ss

16:17 Oct 31, 2014

Nyabuhikye, Ibanda, 4.85 Kms

Kisyoro ss

13:40 Aug 19, 2014

Isingiro Town Council, Isingiro, 9.18 Kms