St. Thomas Moore Secondary School Minakulu

11:16 Mar 11 2015 Bobi, Gulu

Description
Scope: 2 classrooms, 1 laboratory and 2 No. 5-stance lined VIP latrine blocks.

Contract signed: 19-Dec-2011. Site handed over: 19-Dec-2011. Works commenced: 04-Jan-2012. Original completion date: 21-Apr-2012.

Contract sum: UGX 301,635,998. Amount released to school: UGX 301,635,998 (1st 50% on 08-Feb-2012 and 2nd 50% on 26-Nov-2012). Amount accounted for: UGX 286,151,912 (95%). Outstanding advance: UGX 15,484,086 (15%).

Physical progress: 100%. Works completed and furniture supplied. However, defects not yet corrected.

1 no. rain water tanks (10,000 litre capacity) installed by CRESTANKS.

8 no. bookshelves delivered by M/S ZHEJIANG HOLLEY INTERNATIONAL CO. LTD.

UMEME mains power connection to school existing. Solar power installed under ERT project. Water supply from existing 1 No. borehole installed at school.

Follow up actions:

(i) Ministry to issue final certificate to close the project.
(ii) School to submit final accountability to Ministry.
(iii) School to budget for Operation and Maintenance of facilities.
Additional Data
Phase: II
Contractor: AMBROSE CONSTRUCTION CO. LTD
Works Compliant with Specifications: Yes
Project Status: complete
School Completed (with Furnishing)?: Yes

Credibility: UP DOWN 0
Leave a Comment
Name:
Email:
Comments:
Security Code:
Captcha

Additional Reports

Opit SS

16:24 Jun 26, 2014

Lakwana, Gulu, 10.85 Kms

Iceme Girls SS

13:10 Jun 26, 2014

Iceme, Oyam, 15.11 Kms

Koro SS

14:58 Jun 26, 2014

Koro, Gulu, 15.84 Kms

Atapara ss

13:04 Dec 18, 2014

Kamdini, Oyam, 17.97 Kms

Gulu SS

09:46 Jun 27, 2014

Bar Dege Division, Gulu Municipality, Gulu, 19.76 Kms